Construction work main steps stages:


o Project area clearance: completed

o 22kV transmission line construction: completed

o Access Road and access bridge construction: completed

o Civil work: underway

Download NNHPP's progress report for Feb 2008  

CONSTRUCTION WORK PROGRESS Construction work - main stages:
  •  
    • Project area clearance: Completed
    • 22kV transmission line construction: Completed
    • Access road and access bridge construction: Completed
    • Civil work: 80% completed
    • Forebay: Exavation completed.
    • Weir: Left bank  concrete construction started
    • Water Way: Under construction
    • Power House: Excavation 90% completed and foundation work to be started soon