CONSTRUCTION WORK PROGRESS Construction work - main stages:
-
- Project area clearance: Completed
- 22kV transmission line construction: Completed
- Access road and access bridge construction: Completed
- Civil work: 80% completed
- Forebay: Exavation completed.
- Weir: Left bank concrete construction started
- Water Way: Under construction
- Power House: Excavation 90% completed and foundation work to be started soon