Work Progress

bottom menu

CONSTRUCTION WORK PROGRESS (last update 17th march 2008)

Download NNHPP's progress report for Feb 2008 (right click on the icone + save as) : pdf link

 

Construction work main steps stages:

    • Project area clearance: completed
    • 22kV transmission line construction: completed
    • Access Road and access bridge construction: to be started very soon
    • Civil work: to be started very soon

As soon as the last details on the project’s final design will be set (March 2008), the Civil construction work will start on site.
Meanwhile the construction of the 22kV transmission line has been completed by EDL Bokeo branch within 8 weeks.

 

 

The 6.4km long transmission line, built in accordance with the EDL standards and requirements, will transport the Nam Nhone production from the power house to the Bokeo province power grid. It will be used during the construction period to supply the construction site with the necessary energy to power the construction equipment.

 



Transmission line poles before erection                                   Erected 12m concrete pole        

    

Nam Nhone HPP completed transmission line

 